 |
Muskegon
County
Project Fact Sheet |
| Project
Description:
|
The Muskegon County
Michael E. Kobza Hall of Justice -
Phase II project entails demolition and renovation to many areas
of the building.
Phase II will consist of renovations done to only the interior
areas of the building. The Sheriff's Office will have a
new booking, visiting and storage area. Parts of floors
four and six will have work done and some work will be done to
court room one on the first floor. Complete demolition and
renovations will be done to floors three and five.
When this phase of the renovations are complete the fourth floor
will have the Jury Commission and Law Library. The third
floor will house the Family Court and the snack bar will return
to its original location and the
fifth floor will have all the Probate Court and the
Prosecutor's Offices.
The demolition of existing offices and renovations to the new
offices will use modular furniture for more efficient use of
space on each floor.
Relocated Offices: The following offices have been permanently
or temporarily relocated during the renovations to:
Family Court - 1611 East Oak Street
Prosecutor - 131 East Apple Avenue
Drain Commission - 141 East Apple Avenue
State Probation - 131 East Apple Avenue |
|
|
| Start
Date:
|
November
2001
|
| Anticipated Completion
Date:
|
May
2003
|
| Funding
Source:
|
Local
- base bid from contractor $2,832,000
|
| Project
Features:
|
This
project is intended to renovate the interior of the
Hall of Justice for the employees and general use public making
more efficient use of space. When the project is complete
all six floors of the Hall of Justice will have remodeled
departments and , restroom facilities. |
| Architect/Engineer: |
Hooker/DeJong
|
| General
Contractor: |
Clifford
Buck Construction
|
| Status: |
Thursday,
June 17, 2002
The third floor of the Hall of Justice is currently on schedule to be completed by the end
of July 2002. Light fixtures and ceiling tiles are being installed. Most of the drywall work is
completed and the painting contractor has started to paint some areas. Painting to the door
frames has also started. Custom finished woodwork is being placed in the hearing room. The
carpet has also been delivered and rolled out for installation in some areas. The furniture
installers have begun the staging of office furniture in one of the completed areas on the third floor.
Thursday,
May 9, 2002
Demolition on the third floor is complete and significant progress has been made on the renovation.
The old wall unit heating system has been removed and the new air handler and duct work is being installed.
Steel framing has been put in place for wall locations on perimeter walls and interior walls.
Some sheet rock has been installed creating some of the meeting rooms and offices.
Electrical outlets and conduit have been placed in the stud work in all necessary locations.
Insulation has been inserted between some of the studs of the interior meeting room walls for noise dampening.
Work to the Sheriff's jail area has been completed
Friday,
February 20, 2002
Demolition
of the third floor of the Hall of Justice is 95% complete.
Some of the this demolition included the partial removal of the
old HVAC system, abatement, removal of plumbing fixtures,
electrical fixtures, ceiling tiles, carpet and floor tiles.
The contractor has begun laying out the location of where
permanent walls will be built. The mechanical contractors
have also started placing the locations of new electrical, HVAC
and plumbing. The new air handler has been assembled and
tested at the factory and is ready for shipping to Muskegon.
The new visitation and conference area in the jail are nearly
finished with the exception of painting, tile and carpet
installation. On Thursday, February 14, 2002 the
contractor started the temporary relocation of the booking area
so that demolition may commence. The storage area for
inmate belongings is 75% complete.
Both the third floor renovation and the jail renovation are on
schedule with no foreseen problems.
Thursday,
January 11, 2002
On
January 7, 2002, Insulation and Environmental Services started
demolition on the 3rd floor of the Hall of Justice building.
They have been removing temporary walls and taking out ceiling
tiles. Pressures and Pipes has also started to disconnect
plumbing and Allied Electric has started to disconnect power and
removing electrical fixtures also on the 3rd floor.
Work has begun on the expansion of the booking and visitation
area of the jail. The foundation has been poured for the
expansion of the storage area in the jail as well as having
holes cut in the existing storage area to place steel I-beams to
support the ceiling of the expansion.
|
|